Showing posts with label Bridge Engineering. Show all posts
Showing posts with label Bridge Engineering. Show all posts

Thursday, September 03, 2026

Balanced Cantilever Bridge: Structural Design, Construction Methodology and Step-by-Step Process

 

Balanced Cantilever Bridge: Structural Design, Construction Methodology and Step-by-Step Process

Introduction

The balanced cantilever method allows a bridge superstructure to be constructed progressively from the piers, with segments extending in opposite directions. In the method described in this technical document, the superstructure is constructed using cast-in-place segmental prestressed concrete (PSC) box-girders and a Cantilever Form Traveler (CFT).

This article explains the construction methodology, major equipment, reinforcement and concreting sequence, prestressing and grouting operations, stitch-segment construction, and key safety considerations.

Source note: This article is an editorial adaptation of the technical paper Method Statement for Construction of Balanced Cantilever Bridge by using Cast-in-Place Segmental PSC Box-Girders along with Reports on Structural Analysis and Design by Sandipan Goswami. The original document contains detailed project-specific drawings, specifications, calculations and method statements.


What Is a Balanced Cantilever Bridge?

A balanced cantilever bridge is a bridge in which the superstructure is constructed progressively from a pier in the form of cantilever arms extending in opposite directions.

The two cantilever arms are constructed in a balanced sequence so that construction loads are controlled around the pier. Once the cantilevers from adjacent piers approach each other, they are connected through a stitch segment, creating continuity across the span.

For the construction methodology described in the source document:

  • Segmental construction is carried out using a Cantilever Form Traveler (CFT).

  • Typical segments are cast progressively from the pier.

  • The segments are approximately 5 m long in the described arrangement.

  • Prestressing is carried out after the required concrete strength is achieved.

  • Segments S1 through S9 form the main cantilever construction sequence.

  • S10 acts as the stitch segment connecting cantilevers from opposite directions.


Why Use the Balanced Cantilever Method?

The principal advantage of balanced cantilever construction is that much of the superstructure can be constructed without extensive temporary support from below.

This makes the method particularly useful when construction conditions include:

  • Deep valleys

  • Rivers and waterways

  • Busy roads or railway corridors

  • Difficult terrain

  • Large bridge spans

  • Locations where conventional staging is impractical

The construction progresses from the pier itself, allowing the formwork and construction equipment to move along with the advancing bridge deck.


Basic Components of the Bridge

A balanced cantilever bridge project typically consists of several major structural elements:

1. Foundation

The foundation transfers loads from the piers into the supporting soil or rock.

2. Piers

Piers support the bridge superstructure and transfer vertical and horizontal forces to the foundation.

3. Hammer Head

The hammer head or pier head provides the support platform from which the balanced cantilever construction begins.

4. PSC Box-Girder Superstructure

The superstructure consists of a prestressed concrete box-girder constructed segment by segment.

5. Cantilever Form Traveler

The CFT is the temporary construction equipment used to support the formwork and freshly placed concrete during segment construction.

6. Stitch Segment

The final connecting segment joins two cantilever arms extending toward each other from adjacent supports.



Construction Sequence of a Balanced Cantilever Bridge

The construction can broadly be divided into the following stages:

Foundation → Pier → Hammer Head → CFT Erection → S1 Segment → S2–S9 Segments → Prestressing → CFT Launching → Stitch Segment → Continuity Prestressing → Grouting → Finishing Works

Each stage requires close coordination between structural engineering, surveying, reinforcement, formwork, concrete, prestressing, quality control and safety teams.


Step 1: Foundation Construction

The first stage is construction of the foundations.

The foundation arrangement depends on the approved structural and geotechnical design. Once the foundation is completed and accepted, pier construction can proceed.



Step 2: Pier Construction

The piers transfer loads from the bridge deck to the foundations.

Pier construction involves:

  1. Reinforcement fixing

  2. Formwork installation

  3. Survey and alignment checks

  4. Concrete placement

  5. Compaction

  6. Curing

  7. Formwork removal and progression

The source methodology assigns specific responsibilities to the execution, QA/QC, survey, safety and planning teams to ensure that construction follows the approved drawings and sequence.


Step 3: Construction of the Hammer Head

The hammer head is an important part of balanced cantilever construction because the Cantilever Form Travelers are initially installed on it.

The hammer head must provide the required geometry, strength and support arrangement for the construction equipment and the first segment.

The source document has a separate construction methodology for hammer heads at fixed piers, including equipment, materials, inspection requirements and safety measures.


Step 4: Erection of the Cantilever Form Traveler

The Cantilever Form Traveler (CFT) is one of the most important pieces of equipment in this construction method.

It supports the formwork while each new concrete segment is cast and then moves forward to the next position.

The major CFT components described in the source include:

  • Main rails

  • Main frames

  • Rear truss

  • Front truss with hangers

  • Bottom form

  • Outer form

  • Inner form


CFT erection sequence

The CFT is assembled on the ground and inspected before erection. Major components are transported to the lifting location and installed using suitable cranes.

The erection sequence includes:

  1. Installation of main rails

  2. Erection of main frames

  3. Installation of rear truss

  4. Installation of front truss and hangers

  5. Installation of bottom form

  6. Installation of outer form

  7. Installation of inner form

  8. Installation of working platforms

  9. Installation and testing of hydraulic systems

The main rails allow the form traveler to advance after completion of each segment.


Step 5: Casting the First Segment

The first segment, S1, is constructed together with the hammer head according to the described methodology.

After S1 is completed, the subsequent segments are constructed progressively using the CFT.

The source document specifies approximately 5 m segment lengths, with prestressing carried out after casting each segment. Reinforcement remains continuous through the segment construction sequence.


Step 6: Reinforcement and Prestressing Duct Installation

Before concreting, reinforcement and prestressing ducts must be accurately positioned according to the approved structural drawings.

The process includes:

  • Reinforcement cutting and bending

  • Transportation to the deck

  • Reinforcement fixing

  • Web reinforcement installation

  • Soffit reinforcement installation

  • Prestressing duct profiling

  • Anchorage installation

  • Bursting and helical reinforcement

  • Sealing of duct joints

Particular attention is required for the geometry of prestressing ducts because their position directly affects the intended prestressing profile.

The source requires the HDPE ducts to be firmly secured so that they do not move during concrete placement.


Step 7: Inner Formwork and Deck Reinforcement

After completion of soffit and web reinforcement, the inner formwork is installed.

The inner form is aligned using survey equipment and secured using the specified PT bars and supporting arrangements.

Deck reinforcement is then installed along with the prestressing ducts.

The duct profile must follow the specified ordinates and smooth curves shown in the approved drawings.


Step 8: Concrete Pouring

Once reinforcement, formwork and prestressing ducts have been inspected and approved, concrete placement can begin.

The source methodology specifies M50 grade concrete for the described segment construction.

Concrete is transported from the batching plant using transit mixers and delivered to the segment through a concrete pump and pipeline system.

Recommended pouring sequence in the source

The concrete is placed in the following general sequence:

Soffit → Webs → Deck

During web concreting, concrete is placed alternately on the median and ROW sides to maintain an appropriate construction sequence.

Adequate vibration is essential for proper compaction, but the vibrator must not directly damage the prestressing ducts.

Continuous concrete placement is also emphasized to minimize the possibility of cold joints.


Step 9: Curing

After concrete placement, proper curing is essential to achieve the required strength and durability.

The methodology specifies curing of exposed surfaces for 14 days, using water or curing compound. Deck slab curing may be carried out using ponding or wet coverings such as gunny bags.


Step 10: Prestressing of Each Segment

Prestressing is one of the most critical operations in PSC bridge construction.

According to the source methodology, prestressing is carried out after the concrete reaches the specified minimum compressive strength.

For the described segment operation, stressing is undertaken after the concrete achieves 35 MPa or after three days, whichever is later.

The process generally involves:

  1. Preparing the prestressing strands

  2. Threading strands through ducts

  3. Installing bearing plates

  4. Installing wedges

  5. Positioning the stressing jack

  6. Applying the specified stressing force

  7. Measuring elongation

  8. Comparing actual and expected results

  9. Recording stressing data

The stressing force and sequence must always be governed by the approved design and construction drawings.


Step 11: Grouting of Prestressing Ducts

After stressing, the prestressing ducts are grouted.

Grouting protects the prestressing strands and fills the duct surrounding the tendons.

The source methodology includes:

  • Cleaning the ducts with water and compressed air

  • Preparing cement grout

  • Maintaining the specified water-cement ratio

  • Pumping grout through the duct

  • Removing trapped air

  • Monitoring grout flow

  • Closing vents after filling

  • Applying the required pressure

The described procedure specifies a water-cement ratio between 0.40 and 0.45 for the grout.


Step 12: Launching the CFT to the Next Segment

Once the segment has been cast, stressed and cleared for the next operation, the CFT is moved forward.

The launching sequence is critical because the heavy form traveler temporarily moves over the already completed structure.

The methodology includes:

  1. De-stressing and removing rail anchors

  2. Engaging launching wheels

  3. Moving the rails forward

  4. Locking the rails in the new position

  5. Releasing the required formwork connections

  6. Moving the CFT forward

  7. Re-establishing the required support arrangement

  8. Aligning the traveler

  9. Securing the rear tie-down

The source specifically states that no load or personnel should be permitted on the working platform while the form traveler is being launched.


Step 13: Repetition of the Segment Cycle

The construction cycle is then repeated.

A simplified sequence is:

Formwork → Survey → Reinforcement → Duct Profiling → Inspection → Concrete → Curing → Prestressing → Grouting → CFT Launching

This cycle continues from one segment to the next.

The source describes segments S2 through S9 as progressively constructed using the CFT, with S10 acting as the stitch segment.


Step 14: Stitch Segment Construction

The stitch segment is the final connecting portion between two cantilever arms.

Once the cantilever arms from adjacent piers approach each other, the gap between them is closed using the stitch segment.

This is a particularly sensitive stage because temporary conditions, thermal effects, geometry and construction loads must be carefully controlled.

The source describes two possible arrangements for stitch-segment casting, including a hanging shutter arrangement and a CFT-based arrangement.

Sleeve holes provided in the previous segment are used for temporary shutter support where required. Counterweights and temporary holding arrangements are also used in the described methodology to control movement and thermal effects during stitch casting.


Step 15: Soffit Cable Prestressing

After the stitch segment has been completed and the required concrete strength has been achieved, soffit cables are stressed according to the approved sequence.

The source provides a specific stressing sequence for B1 through B8 cables.

Importantly, the required concrete strength varies according to the cable and stage of construction. The document states that B8 stressing begins after the stitch segment reaches the specified minimum strength, while other soffit cables are stressed after higher concrete strength is achieved.


Structural Analysis and Design Considerations

Balanced cantilever construction is not simply a construction technique; it is closely linked to structural analysis.

Stage analysis is described as a method for considering changing forces and deflections over the life of the bridge. The document also refers to design reports based on AASHTO-LRFD, BS/Eurocode 2 and IS/IRC approaches.

For actual bridge projects, structural analysis and design must be carried out by qualified bridge engineers using the governing project specifications, applicable codes, approved design criteria and verified structural models.


Codes and Specifications

The source document identifies several Indian standards and specifications relevant to the described construction methodology.

These include:

  • MoRTH Specifications for Roads and Bridges

  • IS 1343 – Prestressed Concrete Code of Practice

  • IS 14268 – Low Relaxation Prestressing Strand

  • IRC-18 – Prestressed Concrete Road Bridge Design Criteria

The document also references sections covering materials, formwork, reinforcement, structural concrete, prestressing and superstructure works.

The applicable code requirements should always be verified against the latest project-approved editions before construction.


Major Equipment Used

A balanced cantilever bridge project requires specialized construction equipment.

Major equipment identified in the source includes:

  • Heavy-capacity crane

  • Pick-and-carry crane

  • Trailer

  • Concrete pump

  • Transit mixers

  • Batching plant

  • Curing pump

  • Bar cutting machine

  • Bar bending machine

  • Welding equipment

  • Needle vibrators

  • Prestressing jacks

  • Grout pump

  • Survey equipment

  • Hydraulic power pack

  • Cantilever Form Traveler


Quality Control and Inspection

Quality control is required at every stage of construction.

Important records identified in the source include:

  • Material and mix-design approval

  • Request for inspection

  • Inspection checklists

  • Approval to place concrete

  • Concrete batch slips

  • Concrete pour records

  • Prestressing/stressing records

For a PSC bridge, accurate documentation of concrete strength, reinforcement, duct installation, stressing force, elongation, grouting and geometry is particularly important.


Survey and Geometry Control

Geometry control is one of the most important aspects of balanced cantilever construction.

Every segment must be positioned accurately in terms of:

  • Longitudinal alignment

  • Transverse alignment

  • Elevation

  • Deck gradient

  • Cross slope

  • Segment geometry

  • Prestressing duct profile

The source assigns responsibility for alignment and elevation to the Survey Engineer, while shutter alignment is checked before reinforcement and concreting.

Small errors can accumulate as multiple cantilever segments are constructed, making systematic survey control essential.


Safety During Balanced Cantilever Construction

Balanced cantilever bridge construction involves work at considerable height, heavy lifting, temporary structures, hydraulic equipment, prestressing operations and large quantities of concrete.

Safety therefore has to be integrated into every construction activity.

Important safety measures include:

  • Proper PPE for all personnel

  • Safety helmets and reflective jackets

  • Fall-protection systems

  • Barricading of lifting zones

  • Certified cranes and lifting equipment

  • Inspection of shackles and slings

  • Trained crane operators

  • Experienced signalmen

  • Guide ropes during lifting

  • No personnel within the crane swing radius

  • Secure access ladders and platforms

  • Adequate lighting

  • First-aid facilities

  • Good housekeeping

  • Proper fire protection near welding operations

The source specifically emphasizes crane planning, lifting radius, safe working capacity, inspection of lifting accessories and exclusion of personnel from lifting zones.


Why the Stitch Segment Is So Important

The stitch segment may appear to be a relatively small portion of the bridge, but structurally and from a construction perspective it is extremely important.

Before continuity is established, the two cantilever arms behave as separate construction elements.

The stitch segment establishes the connection between them.

During this operation, engineers must carefully control:

  • Geometry

  • Temperature effects

  • Temporary loads

  • Counterweights

  • Formwork

  • Reinforcement continuity

  • Prestressing sequence

  • Concrete strength

  • Survey readings

The source describes temporary holding arrangements specifically to counter movement associated with thermal stresses during stitch-segment casting.


Key Engineering Challenges

Balanced cantilever bridge construction requires close control over several factors.

1. Construction-stage stability

The bridge behaves differently during construction compared with its final completed condition. Each construction stage therefore needs to be considered.

2. Geometry control

Errors in one segment can affect subsequent segments and ultimately the closure between cantilevers.

3. Prestressing

Prestressing forces, elongation and stressing sequence must correspond to the approved design.

4. CFT operation

The form traveler is a major temporary structure and must be safely supported during both casting and launching.

5. Concrete quality

Consistent concrete quality, workability, compaction and curing are essential.

6. Stitch-segment closure

The final connection between cantilever arms requires careful control of temperature, geometry and temporary loading.

7. Safety

Most major construction operations occur at height and involve heavy equipment, making safety planning fundamental.


Balanced Cantilever Construction: A Simplified Flowchart

Foundation Construction

Pier Construction

Hammer Head Construction

CFT Assembly & Erection

S1 Segment Construction

Reinforcement & Duct Installation

Concrete Pouring

Curing

Prestressing

Grouting

CFT Launching

S2–S9 Segment Construction

Approach of Adjacent Cantilevers

Stitch Segment Casting

Continuity / Soffit Cable Prestressing

Final Grouting & Finishing Works


Advantages of the Balanced Cantilever Method

The method offers several important advantages for suitable bridge projects:

Minimal ground-level support

Because construction proceeds from the piers, extensive temporary staging beneath the bridge can often be avoided.

Suitable for long spans

The method is particularly useful for bridges where conventional span-by-span construction is difficult.

Repetitive construction cycle

Once the CFT system is established, segment construction follows a repeatable sequence.

Reduced obstruction below the bridge

This can be particularly useful over roads, rivers, railway corridors and difficult terrain.

High degree of construction control

The segment-by-segment process allows engineers to monitor geometry, concrete quality and prestressing at each stage.


Balanced Cantilever Bridge vs Conventional Construction

ParameterBalanced CantileverConventional Staging
Ground supportLimited requirementOften significant
Deep valleysHighly suitableDifficult
Water crossingsSuitableCan be challenging
Long spansSuitableMay require extensive temporary works
Construction equipmentSpecialized CFT requiredConventional formwork/staging
Geometry controlHighly criticalCritical
Construction sequenceSegmentalSpan/formwork based
PrestressingIntegral to constructionDepends on structural system

Lessons for Civil Engineering Students

Balanced cantilever bridges provide an excellent example of how structural design and construction methodology are interconnected.

A civil engineering student studying this method should understand more than just the final bridge structure. The important learning areas include:

  • Prestressed concrete

  • Structural analysis

  • Construction-stage analysis

  • Formwork design

  • Temporary works

  • Reinforcement detailing

  • Concrete technology

  • Surveying and geometry control

  • Prestressing operations

  • Grouting

  • Construction safety

  • Quality assurance and quality control

  • Project planning

The bridge is not built in its final structural condition from the beginning. Its behaviour changes continuously as each segment is added.

That is what makes balanced cantilever construction particularly interesting from an engineering perspective.


Conclusion

The balanced cantilever method is an advanced bridge construction technique that combines prestressed concrete technology, segmental construction, specialized formwork systems and construction-stage structural control.

The methodology described in the source document demonstrates how a bridge can be progressively constructed using a Cantilever Form Traveler, with each segment undergoing reinforcement fixing, duct installation, concrete placement, curing, prestressing and grouting before the construction equipment advances to the next position.

The final stitch segment establishes continuity between adjacent cantilever arms, after which additional prestressing and finishing operations complete the structural system.

For engineers and students, balanced cantilever bridge construction is a valuable example of how design, analysis, construction planning, temporary works, quality control and safety must work together to deliver a complex infrastructure project successfully.


Frequently Asked Questions

What is a balanced cantilever bridge?

A balanced cantilever bridge is a bridge constructed progressively from its piers, with cantilever arms extending in opposite directions and subsequently connected to form continuous spans.

What is a Cantilever Form Traveler?

A Cantilever Form Traveler is specialized temporary construction equipment used to support formwork and freshly cast concrete during segmental balanced cantilever construction.

What is a stitch segment?

A stitch segment is the connecting segment used to join two cantilever arms constructed from adjacent supports.

Why is prestressing used?

Prestressing improves the structural performance of the concrete box-girder and enables the bridge to efficiently carry the required loads over relatively long spans.

What concrete grade is mentioned in the source methodology?

The described segment construction methodology specifies M50 grade concrete. Actual project requirements must always be based on the approved design and specifications.

What are the major safety concerns?

Major concerns include work at height, heavy lifting, CFT launching, prestressing operations, temporary stability, crane operations and falling-object risks.


Technical Reference

Title: Method Statement for Construction of Balanced Cantilever Bridge by using Cast-in-Place Segmental PSC Box-Girders along with Reports on Structural Analysis and Design

Author: Sandipan Goswami

Primary subjects: Balanced Cantilever Bridge, PSC Box-Girder, Segmental Construction, Cantilever Form Traveler, Prestressing, Structural Analysis and Construction Methodology.

The original document is organized into four major parts covering balanced cantilever segment construction, foundations/piers/superstructure, hammer-head construction and tack coat/bituminous concrete works, followed by references and design summaries.


📚 Content provided by: Manvender Nigam

Friday, February 12, 2021

Where is a gantry girder most used?

  1.  The purpose of gantry Girder is to pick and move heavy machinery components within industrial building.
  2. A girder is commonly used many times in the building of bridges.
  3. Gantry girders are used in workshops/factories for movement of cranes which lifts material and shifts from one location to other.
  4. Overhead travelling cranes are used in factories and workshops to lift heavy materials, equipment's, etc. and to carry them from one place to the other.


Thursday, April 11, 2019

Iconic Signature Bridge In Delhi

The bridge was inaugurated on 4th November 2018. Signature Bridge is an elaborated cantilever span cable- stayed bridge, comprising of an asymmetrical inclined namaste-shaped Steel Pylon of 154 m height.

                         Total length of cable stayed bridge from expansion joint to expansion joint is 575 meters, with main cable- stayed span of 251 meters supported with 15 sets of cables on one side and counterbalanced by 8 back stay cables attached at a rocker bearing on axis 23. 
The bridge's steel and concrete composite deck has dual carriageway of 4 lanes, 14 m each, with about 1.2 m central verge, space for anchoring cables, maintenance walkway and crash barrier on either side of the central verge. The outer to outer width of bridge is around 35.20 m and the approach span are about 36 m long. Spherical bearings are provided on all the piers. Pendulum bearing are provided for back stay.
                          The Steel Pylon of around 154 meters from top of the bearings consists of two legs made up of steel boxes, which merge into one upper pylon body zone made up of a load bearing skin stiffened by internal stiffeners and bracing s, where the cable supporting the main span and the back stays are anchored. Each of the pylon legs consists of a hollow steel box, which would be roughly 50 - 80 meter high. The upper end is the kink diaphragm, which is the transition from pylon leg to the pylon body.
                            It also has a pylon head, made up of beams and columns in steel structure with a glass cladding. Major part of the steel for pylon is of grade S355. In very highly stressed anchorage zones, S460 grade steel is also used. Each leg of pylon rests on spherical bearings to transmit vertical loads of around 17,000 T.
                             The deck spans 32 m in transverse direction for B lanes of traffic,4 lanes in each direction. The composite deck consists of two main girders (I- shaped) in longitudinal direction and cross girders at 4.5 m spacing along the deck. Spans are of 13.5 m long on the cable- supported part, 36 m on the approach  spans, which are supported over concrete columns. Most part of the deck slab is made up of full depth prefabricated concrete elements of varying thickness from 250 to 350 mm, stitched in- situ over steel girder flanges. In highly stressed areas, near pylon base and backstay anchorage, in-situ concrete up to 700 mm thick is used.
                                The cables are made up of bundles of parallel 15.7 mm strands of class 1.770 MPa, protected against corrosion with hot dip galvanization & outer PE- pipes. Depending on the location the number of strands per cable varies from 55 to 123 nos. at the main span and is 127 nos. for each backstay.
                                 Under the axis A and C, independent foundations are provided up to the depth of 20 m below ground level as generally rocky stratum was geotechnically determined at that level.
                              There are 6 numbers of open foundation resting on rocky strata at a depth of about 20m. 
                              As the open foundation were to be rested on rock by about 20 m below the ground level, sheet - piled cofferdam was used for excavation by Elevated Lateral Support System (ELS).
                           All well foundation were required to be done adopting jack down method of sinking for controlling the sinking operation without tilt and shift. 

Friday, April 05, 2019

Bogibeel, The longest Rail- Cum - Road Bridge in India

Bogibeel bridge is a combined road and rail bridge over the Brahmaputra river in the north eastern Indian state of Assam between Dhemaji district and Dibrugarh district, which was started in the year 2002 and took a total of 200 months to complete, heavy rainfall in the region being the main cause for the slow progress. Bogibeel river bridge is the longest rail-cum-road bridge in India measuring 4.94 kilometres over the Brahmaputra river. As it is situated in an earthquake-prone area it is India's first bridge to have fully welded steel-concrete support beams that can withstand earthquakes of magnitudes up to 7 on the Richter Scale.

Bogibeel bridge
This is also Asia’s 2nd longest rail-cum-road bridge and has a serviceable period of around 120 years. This is the 5th longest bridge in India after Bhupen Hazarika Setu, Dibang River Bridge, Mahatma Gandhi Setu and Bandra-Worli Sea Link. The bridge was constructed by a consortium of construction companies headed by Hindustan Construction Company. It was inaugurated by prime minister Narendra Modi on 25th December 2018 on the occasion of Good Governance Day.


The Bogibeel bridge traces its origins to the Assam Accord of 1985 and was one of several major infrastructural projects to be set up in Assam in accordance with the pact. It was sanctioned by the Government of India in 1997-98 and was expected to be completed by the end of the Ninth Five Year Plan. The foundation of the bridge was laid in January 1997 by Prime Minister H.D.Deva Gowda, but its construction was inaugurated only in 2002 by Prime Minister, A.B. Vajpayee. The project was to be completed in six years following the inauguration, however the work did not begin until 2007, owing to lack of funds and attention. Consequently, that same year, the Bogibeel bridge was granted a national project status by the Government of India in 2007 by Prime Minister Manmohan Singh, but the implementation was slow, notwithstanding a Congress government in Assam. The Union Ministry of Finance funded 75% of the project costs while the Ministry of Railways financed the rest. The actual work on the project only began in 2011.

The design of Bogibeel bridge has 39 spans of 125 m and a superstructure of composite welded steel truss and reinforced concrete. It is designed to carry a double line 1,676 mm (5 ft 6 in) broad gauge railway on the lower deck and a 2-lane road on the upper deck. With its proximity to the China border, the bridge also has tremendous significance for India's defence and has been built strong enough to support the movement of tanks and even fighter jet landings. It is the longest combined rail and road bridge in India and second longest bridge in Assam over the river Brahmaputra after Bhupen Hazarika Setu which is a road bridge of length 9.15 km.

#Bogibeel, The #longest #Rail- Cum - #Road #Bridge in #India

Monday, March 12, 2018

The 10 Longest Floating Bridges in the World

2
Lacey V. Murrow Memorial Bridge, SeattleU.S.A, 2,020 meters, 1940. The bridge carries the eastbound lanes of Interstate 90 across Lake Washington from Seattle to Mercer Island, Wash. The world’s first floating bridge to be built using concrete pontoons, it was designed by engineer Homer Hadley, and constructed by the Puget Sound Bridge and Dredging Co., at a price tag of $9 million. While undergoing reconstruction in 1990, an 850-m-long section of the bridge sank when a storm filled one pontoon. The rebuilt bridge reopened in 1993, at a cost of $93 million

Monday, February 05, 2018

How to Perform Pile Integrity Test?

Pile integrity test (PIT) is low strain impact integrity test, is a common non-destructive test method for the
-Evaluation of pile cross-sectional area and length, the pile integrity and continuity, as well as consistency of the pile material.
-Forensic evaluations on existing piles, or quality assurance in the new construction.
The integrity test is applicable to driven concrete piles and cast-in-place piles.
Low strain impact integrity testing provides acceleration or velocity and force (optional) data on slender structural elements. Sonic Echo (SE) and Impulse Response (IR) are employed for the integrity test on deep foundation and piles.
The PIT method works best for column type foundations, such as piles and drilled shafts.

How to Perform PIT?

The pile head surface should be accessible, above water, and clean of loose concrete, soil or other foreign materials resulting from construction. Any type of contamination should be removed (using a grinder) to reach to solid and sound concrete surface. This step is so vital, because then connection between the sensor and concrete should be solid (firm contact). The location of the sensor should be selected away from the edges of the pile. The integrity testing should be performed no sooner than 7 days after casting or after concrete strength achieves at least 3/4 of its design strength, whichever occurs earlier.
A hammer (with or without force measurement unit) is used for impacting pile top; the impact should be applied axially with the pile. Motion transducer should be capable of detecting and recording the reflected echos over the pile top. Acceleration, velocity, or displacement transducers can be used for this purpose. At the minimum, acceleration transducer should have an Analog to Digital Converter with 12 bit resolution; and a Sample Frequency of at least 25 KHz.
The distance between the impact location and the sensor should be no larger than 300 mm. Several impacts are applied to the top of the pile. The reflected echos are then recorded for each individual impact. As an alternative, the average can be determined and used. As mentioned earlier, acceleration transducer can be used for the purpose of this test. In this case, the apparatus shall provide signal conditioning and integrate acceleration to obtain velocity. The apparatus shall balance the velocity signal to zero between impact events.

Wednesday, January 17, 2018

Bridge Construction Equipment

Underslung Movable Scaffolding Systems
Overhead Movable Scaffolding Systems
Underslung Self-Launching Gantries
Overhead Self-Launching Gantries
Underslung Form Travelers
Overhead Form Travelers
Beam Launchers
Precast Full-Span Systems



    Thursday, March 30, 2017

    Which type of multiple-cell box girder is better, cells connected by top flanges or cells connected both by top and bottom flanges?

    When the depth of a box girder bridge exceeds 1/6 or 1/5 of the bridge width, it is recommended to be designed as a single cell box girder bridge. However, if the bridge depth is smaller than 1/6 of the bridge width, then a twin-cell or multiple cell is a better choice. However, even for wider bridges with small depths, the number of cells should be minimized
    because there is not much improvement in transverse load distribution when the number of cells of box girder is increased to three or more. For multiple-cell box girders, there are generally two arrangements. The first one is that independent cells are connected by their top flanges only while the other one is that the cells are connected both at the top and bottom flanges. From the structural point of view, it is recommended to adopt the second arrangement. For the case of cells connected by top flanges only, their flanges are heavily stressed in the transverse direction owing to flexure which cannot be effectively distributed across the cross section.




    boxgirder

    Ref: Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

    Friday, March 24, 2017

    What is sucker deck principle for variable depth bridge decks?

    For a variable depth bridge deck, the depth of continuous multi-span bridge deck is increased in pier supports and this absorbs sagging moments in the mid-span with the consequent increase in hogging moments in pier supports.




    Thursday, March 23, 2017

    What are the advantages of piers constructed monolithically with the bridge deck over usage of bearings?




    Basically, piers constructed monolithically with the bridge deck are advantageous in the following ways:
    1. In this way, it saves the construction cost of bearings by using monolithic construction between bridge deck and piers. Moreover, it is not necessary to spend extra effort to design for drainage details and access for bearing replacement. On the other hand, in maintenance aspect substantial cost and time savings could be obtained by using monolithic construction instead of using bearings as bridge.
    2. Monolithic construction possesses the shortest effective Euler buckling length for piers because they are fixed supports at the interface between bridge deck and piers.
    Note: Monolithic construction means that piers are connected to bridge decks without any
    joints and bearings.
    Ref: Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

    Saturday, March 18, 2017

    For the loading pattern to obtain maximum positive moment in a span of a continuous beam, why should alternative spans on each side of the span be loaded?




    To acquire a maximum sagging moment in a span of a continuous beam, the general rule is to load the span under consideration and alternative spans on each side of the span. To account for this rule, let’s consider the following example. For instance, loads are applied to the mid-span of a multiple-span continuous beam. It is noticed that this loads induce positive moments near mid-span in all even spans. Therefore, if all even spans are loaded simultaneously, this will result in the increase of positive moments in all other loaded spans. Similarly, to obtain maximum negative moment at a support, load adjacent spans of the support and then alternative spans on each side.




    What are the potential advantages of continuous multiple-span deck over simply supported multiple-span deck?





    Movement joints are normally added to bridge structures to accommodate movements due to dimensional changes arising from temperature variation, shrinkage, creep and effect of prestress. However, the provision of excessive movement joints should be avoided in design because movement joints always encounter problems giving rise to trouble in normal operation and this increases the cost of maintenance. Some designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. However, the effect of continuity is disabled by this excessive introduction of movement joints. 




    From structural point of view, the use of continuous deck enhances the reduction of bridge deck thickness. Moreover, deck continuity allows the potential increase in headroom in the mid-span of bridges by using sucker deck principle.
    Some designers may prefer to employ the use of simply supported multiple-span deck to guard against possible occurrence of differential settlements. However, the effect of continuity is undermined by the introduction of movement joints. In essence, the structural reserve provided by a continuous bridge is destroyed by the multiple-span statically determinate structure resulting from the addition of joints. Moreover, the reduction of joints in bridge structures represents substantial cost savings arising from the construction and maintenance costs of movement joints. The reduction of deck thickness helps to cut the cost for both the deck and foundation. In particular, the number of bearings in each piers is substantially reduced when compared with the case of simply supported multiple-span deck.

    Ref: A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

    What are the main potential benefits in using the bridge form of precast prestressed beams supporting in-situ concrete top slab?




    The potential benefits of using the bridge form of precast prestressed beams supporting in-situ concrete top slab are:

    (i) For bridges built on top of rivers and carriageway, this bridge form provides the working platform by the precast beams so that erection of falsework is not required.
    (ii) This bridge form generally does not require any transverse beams or diaphragms (except at the location of bridge supports), leading to reduction of construction time and cost.
    (iii) It creates the potential for simultaneous construction with several spans.
    Ref: A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.




    Friday, March 17, 2017

    What is stress corrosion of prestressing steel?

    Stress corrosion is the crystalline cracking of metals under tensile stresses in the presence of corrosive agents. The conditions for stress corrosion to occur are that the steel is subjected to tensile stresses arising from external loading or internally induced stress (e.g. prestressing). Moreover, the presence of corrosive agents is essential to trigger stress corrosion. One of the main features of stress corrosion is that the material fractures without any damage observed from the outside. Hence, stress corrosion occurs without any obvious warning signs.
    This question is taken from book named – A Self Learning Manual – Mastering Different Fields of Civil Engineering Works (VC-Q-A-Method) by Vincent T. H. CHU.

    Friday, February 17, 2017

    Lucknow Metro’s 255m Cantilever Bridge Completed

    The bridge has been designed with a 105m long central span and two 75m long end-spans, and is the only missing piece of the 8.48 km Transport Nagar – Charbagh ‘priority corridor’ of the 22.878 km north-south line which prevents trial runs from commencing on a 2 km stretch between Mawaiya and Charbagh stations.


    Lucknow Metro’s 255m Cantilever Bridge Completed
    Add caption




    Lucknow Metro’s 255m Cantilever Bridge Completed

    Lucknow Metro’s 255m Cantilever Bridge Completed